While the failover is being executed, the status of each step that makes up the recovery plan can be
monitored by going to Recovery Steps tab (highlighted in Figure 53) of the Site Recovery Manager UI on
the recovery site. The UI informs you what steps are currently Running as well as what steps were
completed. There are some steps in a recovery plan that will only be executed during a simulated test.
Mode column. There are also some steps that will only be
executed during an actual failover. These steps are identified by Recovery only under the Mode column.

to start validating that all application services restarted cleanly at the recovery site. In this case, the protected
virtual machine site1-vm5
failed over application services at the recovery site you are now in a position to report the successful failover
to the business and allow the respective business users to access the application services, which are now
being hosted on the recovery site.
NOTE: Site Recovery Manager will automatically perform a re-signature of the replicated iSCSI and FC
datastores in the recovery site, which means LVM.EnableResignature will be set to 1
have access to the replicated datastores in the recovery site. The re-signature that is initiated by Site Recovery
Manager will result in the replicated datastores being presented with a prefix of snap-xxx-.
Site Recovery Manager automatically generates a report for each recovery plan execution. In this instance the
report is for a Site Recovery Manager Run operation against the recovery plan that was selected. The report
is accessible via the History tab and can be viewed by clicking on the View link under the Actions column.
See Figure 42.
The steps to failback services from the recovery site back to the protected site once the disaster event is over
are outlined in section 6.
The following is a recap of the high level tasks executed by Site Recovery Manager when performing a
failover of virtual machines from the protected site to the recovery site via the Run a recovery plan option.

Site Recovery Manager:
 
 